The assembly
1 TECEdrainline-Evo shower channel
2 TECEdrainline drain
3 TECEdrainline assembly feet
4 Drainbase sound insulation mat
Step 1: The closed channel is placed and aligned in the room. This can be easily achieved with the optionally available mounting feet. The drain pipe can be laid under the gutter to save space.
Step 2: Leak test by the fitter: the dip rod is inserted into the opening of the transparent bare-wall protection.
Step 3: Water is poured into the opening. The construction time protection cover does not have to be removed or opened to do this.
Step 4: When handing over to the tiler, the undamaged seal of originality (1) guarantees the status of delivery of the channel from the factory.
Step 5: After filling with screed, the construction time protection is removed and the first layer of the composite seal is applied.
Step 6: The sealing sleeve is installed in the composite seal.
Step 7: Full application of the composite seal
Step 8: After the tiling and grouting: Once the cover has been installed, assembly is complete. The cover can simply be removed for cleaning purposes at any time.